• City sidewalk is in - it may have a "P" carved in it somewhere :-)
  • brick started - insane # of choices here. . .
  • Driveway is in - notice 2" PVC for landscape lights and sprinkler system
  • View from SE corner of property (or how the lake sees the house)
  • No mud finally - pic of finished deck (for reference, that sliding glass door is 6' wide)
  • Notice 6" PVC under the sidewalk - for downspout extension, landscape lighting, and sprinkl
  • Sidewalk is in - yes, it wiggles!  1/13/04
  • laundry room floor is in - 1/13/04
  • molding is painted 1/14/04
  • living room primed - ceilings DONE1/5/04
  • All rooms primed- 1/5/04 - ceilings DONE
  • Kitchen primed1/5/04 stair handrail going on next - ceilings DONE
  • Garage taped 1/1/04 - 14' sheets of drywall!!
  • kitchen and living room taped 1/1/04
  • Kitchen and dining room taped 1/1/04
  • living room taped 1/1/04
  • bedroom drywalled and taped 1/1/04
  • living room drywalled - I wont bore you with the other 40 shots :-)  12/19/03
  • Birdseye view - garage doors and deck are in! 12/18/03
  • Kristi dances a jig on her new deck!  The cedar smell is invigorating!  12/18/03
  • Deck is finished - but they've messed up the handrail.  Kristi doesn't want these bars in the sc
  • Liviing room is starting to take shape 12/18/03
  • Over 80% of upstairs is drywalled. 12/18/03
  • Garage is fully drywalled. They move when they get goin! 12/17/03